On Bronxdale Avenue, a 354,309-square-foot industrial building sits on 7.4 acres next to the Amtrak tracks. Tenants fill it, it produces income, and it has a parking deck. Since October it has also been for sale as a fully entitled site for six buildings and more than 2,300 apartments. The plans include a supermarket, 640 parking spaces and a pedestrian overpass to the future Parkchester/Van Nest Metro-North station, according to Yield PRO's October 5, 2026 report.
Himmel + Meringoff Properties and Affinius Capital bought the site in 2019. They secured the entitlements through the Bronx Metro-North rezoning, which the City Council approved with modifications on August 15, 2024. The offering materials say the station opens in 2027 with a trip of about 21 minutes to Penn Station. Everything else about East Bronx station-area real estate starts from that date. The current public record puts the date later, and the sales around the station show buyers paying ordinary Bronx land prices.
The schedule a buyer should underwrite
The MTA's Penn Station Access project page, updated September 14, 2026, lists 2030 as the current estimated completion. The project covers four accessible stations at Hunts Point, Parkchester/Van Nest, Morris Park and Co-op City, and the MTA says it will cut travel times from the Bronx to Manhattan by as much as 50 minutes.
That 2030 date comes from the MTA's October 2025 capital program report. The original design-build contract set substantial completion for March 2027. The re-baselined schedule moved revenue service to March 2030 and made even that date depend on Amtrak providing track outages and support crews. In the same report, the contractor's own schedule update forecast May 2032, and it put completion of all four stations in December 2030.
The MTA also proposed a way to keep 2027 alive: limited service at Co-op City, Morris Park and Parkchester/Van Nest. That meant five trains in each peak, two reverse-peak trains, and hourly weekday service from 6 a.m. to 8:30 p.m., if Amtrak agreed to schedule and work-rule changes. By May 2026 that option had faded. A May 2026 letter from Reps. Ritchie Torres, Alexandria Ocasio-Cortez, George Latimer, Jim Himes and Rosa DeLauro cited "Amtrak's inability to accommodate the MTA's previous plan for limited early service." The letter said full service could begin in early 2029 if the two railroads agree to prioritize the capital work needed for service, according to the congressional release.
THE CITY's reporting quoted Amtrak spokesperson Jason Abrams, who said the railroad shares "MTA's commitment to bringing Metro-North service to The Bronx as soon as possible." The same story reported that Amtrak has been canceling a dozen Acela trips a week during outages so MTA contractors can work.
Physical work continues. The MTA's September 2026 project newsletter reported structural steel going up at Morris Park and platform utility work at Parkchester/Van Nest.
For underwriting purposes, early 2029 is the best case on record, March 2030 is the MTA's schedule, and May 2032 is the contractor's forecast. 2027 is no longer on the table. A site priced on a 2027 opening is asking the buyer to pay for two to five years of transit access before it exists.
What land next to the station is actually trading for
The market is pricing in only a small part of the train today. The third-quarter 2026 sales record for the southwest Bronx groups Parkchester and Van Nest with the South Bronx. Parkchester recorded one trade for $1.3 million and Van Nest one trade for $1.4 million. The individual deals on and near East Tremont Avenue look like this, set against South Bronx land trades from the same quarter:
| Address | Date | Price | Type | Pricing |
|---|---|---|---|---|
| 1134–1138 E Tremont Ave | July 23, 2026 | $1,300,000 | Small mixed-use/multifamily | $201/SF, $260,000/unit |
| 1740 E Tremont Ave | August 18, 2026 | $1,300,000 | Development site | $104/BSF |
| 633 Wales Ave | August 31, 2026 | $2,425,000 | Development site | $109/BSF |
| 631–633 Bergen Ave | July 8, 2026 | $9,175,000 | Development site | $89/BSF |
| 3565 Third Ave | September 23, 2026 | $12,350,000 | Development site | $84/BSF |
For the five development trades in the submarket in Q3 2026, the median was $89 per buildable square foot. At $104, 1740 East Tremont came in above that median, but below a Longwood site on Wales Avenue that has no Metro-North station planned nearby. A site a short walk from a future 21-minute ride to Midtown's West Side sold within the normal South Bronx range in the third quarter of 2026. The transit story added a modest edge to that price.
The East Tremont site also shows how fast plans and paper move in this corridor. New York YIMBY reported on August 16, 2026 that permits had been filed for a mixed-use building there with 23 residences and 3,611 square feet of commercial space. The recorded trade at $104 per buildable square foot followed two days later.
The pipeline is small-lot, and it is moving
Excluding 1601 Bronxdale, the post-rezoning activity in Van Nest is small-lot work. Permits were filed for a three-story, six-residence building at 581 Van Nest Avenue in September 2025 and for an 11-residence building at 1848 Muliner Avenue in October 2026. In Parkchester, a seven-story, 19-apartment building at 2039 Westchester Avenue received its first certificate of occupancy on June 11, 2026. Down the avenue, Apex Development and Knickpoint Ventures secured $60 million to buy and build a charter school at 1780 East Tremont Avenue, Commercial Observer reported in June 2026.
At this scale, a six-unit or 23-unit building can be permitted, built and leased on its own merits before the first Metro-North train stops. Any transit value arrives as upside after stabilization. At 2,300 apartments and 2.42 million square feet, 1601 Bronxdale works on a much longer timeline. The site is leased to a mix of industrial and commercial tenants and produces cash flow today. For a buyer, the figure to test is how many years of that in-place income the price assumes before redevelopment starts, and whether the leases run long enough to cover a 2029 or 2030 opening.
Hunts Point is on a longer clock, and priced like it
The station-area thesis looks different at each of the four stops. Hunts Point was left out of the 2027 interim proposal, and the MTA's September 2026 newsletter put the start of platform construction there in late 2027.
The neighborhood's one Q3 2026 trade was the Orenco Funding Bronx portfolio: 150 units for $6.65 million on July 28, about $44,000 per unit. That is below the Bronx-wide figure for heavily regulated buildings. In the third quarter of 2026, Bronx assets that were 75% or more rent-stabilized averaged about $68,000 per unit, while free-market buildings averaged $217,000 per unit. The rent-roll gap between stabilized and free-market buildings explains far more of the price difference than distance to the future platform does.
Hunts Point also has new housing on the way. The Doe Fund broke ground in August 2026 on the Casanova Residence at 658–674 Casanova Street, a 96-home project with 38 affordable and 58 supportive units, according to 6sqft.
What this means for a deal priced this winter
The borough-wide numbers point the same way. Bronx multifamily sales totaled $123.5 million across 28 transactions in the third quarter of 2026, down 5% in dollar volume from a year earlier. In this market, buyers are paying for in-place rents and buildable square feet at Bronx prices and treating the Metro-North stations as an option they are not yet paying full value for.
That makes the opening year the variable to check in any station-area offering, from a six-unit lot on Van Nest Avenue to the 7.4 acres on Bronxdale. A pro forma built on 2027 service carries two to three years more transit benefit than the MTA's March 2030 schedule supports. One built on 2030, with an industrial rent roll or a small-building lease-up to cover the gap, matches the record as of this November. If Amtrak and the MTA reach the early-2029 path the congressional delegation described, a buyer who underwrote to 2030 gets that year back as upside.
For context on how stabilized and free-market Bronx buildings are pricing more broadly, our earlier look at whether Bronx multifamily is still undervalued covers the underwriting side, and our Bronx neighborhood page tracks the borough.
FAQ
When will Metro-North trains stop at the new East Bronx stations? The MTA's current estimate is 2030, and its re-baselined schedule targets March 2030 for revenue service. A May 2026 congressional letter said full service in early 2029 is possible if Amtrak and the MTA prioritize the work required for service.
Is any station opening in 2027? The MTA's October 2025 limited-service plan for Co-op City, Morris Park and Parkchester/Van Nest depended on Amtrak, and the May 2026 letter said Amtrak could not accommodate it.
Are station-area development sites selling at a premium? Modestly. In Q3 2026, 1740 East Tremont Avenue in Van Nest sold at $104 per buildable square foot, compared with a $89 median for southwest Bronx development trades that quarter.
If you own or are weighing a building or lot near Parkchester/Van Nest, Morris Park, Co-op City or Hunts Point, The CS Organization pairs neighborhood market knowledge with capital advisory, including refinancings and construction loans, for owners and sponsors deciding when to sell, hold or build ahead of the new stations. Request a valuation or schedule a consultation with our capital advisory team.